Punjab RERA ruled that a homebuyer’s right to timely possession cannot be denied. It directed Omaxe Chandigarh Extension Developers Private Limited to hand over the The Lake project unit and pay interest on ₹88.83 lakh for a delay of more than five years, from October 30, 2018 until possession.

Why It Matters

The ruling reinforces homeowners' right to timely possession under RERA and clarifies interest liability in long-delayed projects.

Timeline

4 Events

Compliance window and potential recovery measures

July 27, 2026

The builder was directed to comply with the order within 90 days of the RERA decision (by July 27, 2026). If not complied, recovery proceedings may be initiated as arrears of land revenue.

RERA order directing possession and interest

April 28, 2026

Punjab RERA found the promoter failed to deliver possession within the agreed timeline and partly allowed the complaint. It directed the builder to hand over possession after obtaining occupancy and completion certificates, and to pay interest on ₹88.83 lakh at SBI's highest marginal cost of lending rate plus 2% from October 30, 2018 until possession. The complainants had paid over ₹75 lakh (more than 90% of the total cost) and had fulfilled their obligations. The authority rejected the builder’s argument that delays were caused by payment defaults and force majeure including COVID-19 (delays predated the pandemic). It denied refunds of charges based on super area since the agreement was executed before RERA came into force, and held that interest paid by the builder under a subvention scheme cannot be claimed again as it would amount to a double benefit.

Possession due date defined in agreement

October 30, 2018

As per the agreement, possession was to be handed over by October 30, 2018. The builder neither completed the project nor offered possession by this date.

Booking by complainant for The Lake project

October 2015

The complainant booked a residential unit in Omaxe Chandigarh Extension Developers Private Limited's The Lake project in October 2015 for ₹88.83 lakh.