KRERA directs BDA to complete NPK Layout and pay Rs 22.46 lakh to homebuyer

KRERA ordered the Bangalore Development Authority to complete the Nadaprabhu Kempegowda Layout with essential infrastructure and to pay ₹22,46,177 as interest for the delay. The decision underscores homebuyer protections under RERA and requires completion of core amenities before possession can be deemed compliant.

Why It Matters

The ruling reinforces homebuyer protections under RERA by insisting on completion of core amenities before handing over possession and requiring compensation for delays.

Timeline

7 Events

KRERA directive to complete project and pay compensation

April 28, 2026

KRERA directs BDA to complete the Nadaprabhu Kempegowda Layout with full infrastructure and hand over the plot within 60 days, and to pay ₹22,46,177 as delay interest to the complainant; the directive is reported in this article dated April 28, 2026.

End of delay-interest period specified

December 21, 2025

Interest on delay period calculated at SBI MCLR+2% ends on December 21, 2025, as per KRERA order.

Possession certificate issued

June 16, 2020

Possession certificate for the site was issued on June 16, 2020.

Lease-cum-sale deed executed

June 10, 2020

A lease-cum-sale deed was executed for the site on June 10, 2020.

Full sale consideration paid

February 5, 2019

Buyer paid the full sale consideration of ₹96.87 lakh by February 5, 2019.

Allotment of site in NPK Layout to buyer

October 11, 2018

Site allotment in Nadaprabhu Kempegowda Layout to Ms. Mridula Krishnapur (Sector B) on October 11, 2018.

Interest on delay period begins

May 24, 2018

KRERA notes that interest on the delay will be calculated at SBI MCLR+2% from May 24, 2018.